The right-field scoreboard and roof deck added in 2024

The ballpark

Renovations at Camden Yards, 2025 to 2027

The largest upgrades since the ballpark opened arrived for 2026, paid for under the 2023 lease, and a second phase is under way for 2027. Facts checked Nov 24, 2026.

Photo: Rock & roll is not dead, CC0, via Wikimedia Commons.

Earlier changes

Camden Yards has been updated in stages since it opened. After 2008 a new HD video display and scoreboard went in below the right-field flag court, with a new sound system in 2009. Before 2011 the lower-bowl seats were replaced, drink rails were added on the Club Level and some skyboxes became party suites. In the 2011–12 off-season the food options grew, the upper-deck concourses were widened and a center-field lounge opened on top of the batter's eye, renamed the Coors Light Roof Deck in March 2024. Around 2012 Janet Marie Smith returned to oversee work that included a sculpture park and the rooftop deck, and six bronze statues of the Orioles' Hall of Famers were unveiled that year.

Phase 1: the 2026 upgrades

On May 6, 2025 the Maryland Stadium Authority approved plans for a new center-field videoboard two and a half times the size of the old one, which dated from 2008. The work drew on $135 million of bond financing that the Board of Public Works had approved in January 2025, and the governor's office called it the largest set of upgrades since the ballpark opened.

  • Video: a 4K center-field board with more than 16.7 million pixels and 1,125 feet of LED ribbon boards.
  • Sound: a new system with more than 900 high-output speakers.
  • Behind the scenes: a control room about twice the size, and the press box moved to the third-base line.
  • Truist Club: the park's first premium club, in the old press-box space behind home plate.
  • Club Level: fully redesigned, with two climate-controlled bars on the first- and third-base sides, a renovated store at Section 244 and a new one at 216.
  • Home Plate Club: renovated over the 2025–26 off-season.
  • PureWager Pavilion: a covered patio under the new videoboard, rentable by groups and open to fans when not booked.
  • Paying: five Amazon Just Walk Out markets, on Eutaw Street and near Sections 17, 23, 35 and 64.

In March 2026 the Orioles also announced a Flag Court Bar, built with Corona: an open-air wraparound bar around the existing flags, serving the Flag Court and Eutaw Street, due after the 2026 All-Star break. The governor's office said the stadium authority would start the next phase after the 2026 season.

The right-field scoreboard and roof deck added in 2024
The right-field scoreboard and roof deck added in 2024. Photo: Rock & roll is not dead, CC0, via Wikimedia Commons.

Phase 2: the 2027 work

On September 29, 2026 the Orioles announced a new social space in the left-field upper deck, sections 382 to 388, which had often been closed in recent years. It will have drink rails, standing-room viewing, tables and chairs, a central bar, concessions and TVs, be open to every ticket holder from Opening Day 2027, and be rentable on non-game days.

On November 17, 2026 the club added more off-season work:

  • A family play zone with a scaled-down ballpark, wiffle ball sets, a family dugout and play structures modelled on the skyline and the B&O Warehouse, due after the 2027 All-Star break.
  • A treehouse-style mascot meet-and-greet space, which the renovations page calls the Birdhouse, in an old ticket office between Gates F and G.
  • Suites 9 to 31 modernized, with some combined into larger premium spaces.
  • A new player dining area and kitchen, and new fire pump, water heaters, emergency generator and HVAC equipment.
  • Restroom work (see below).

Everything except the play zone is due to be working for the Home Opener on Monday, March 29, 2027.

Who pays

The money comes from the state bond authority unlocked by the December 2023 lease. The governor's office says the lease opened up to $600 million authorized by the General Assembly in 2022, and that the stadium authority had issued $305 million of it for the renovation fund by March 2026. See lease and ownership.

Where sources disagree

  • The $135 million: completed upgrades, per the governor's office; bond financing of which $22.7 million covered the videoboard work, per MLB.com.
  • The bond money unlocked: $400 million, potentially up to $600 million, per MLB.com; $600 million per Maryland Matters and the governor's office.
  • The play zone's site: the bullpen picnic area per the press release; the picnic area along Eutaw Street per the renovations page.
  • Restrooms: Club Level and main concourse per the renovations page; main and upper concourses per the press release.
  • The center-field patio: PureWager Pavilion to the Orioles, Scoreboard Social to the governor's office.

Questions

What is new at Camden Yards for 2027?

A social space in left-field upper-deck sections 382–388, modernized suites, a mascot meet-and-greet space and, after the All-Star break, a family play zone.

What changed at Camden Yards in 2026?

A 4K center-field videoboard, 900-plus speakers, the Truist Club behind home plate, a redesigned Club Level and the PureWager Pavilion.

How much did the 2026 Camden Yards upgrades cost?

The governor's office says $135 million; MLB.com says $135 million in bond financing, $22.7 million of it for the videoboard work.

Sources

Facts checked Nov 24, 2026.